At the same time we hope you will recognise that there has been a significant difference to the site and that we are very close to the scheme being completed and ready for use.
Works progressed and completed so far include:
Completed
the mixed border planting scheme
Laid turf in
the orchard area
Planted our
new fruit trees (2 apple, 2 pear and 2 cherry trees)
Completed
installation of all 28 raised planters
Completed
installation of the metal benches
Installed our
litter bin
Provided an
additional wildlife banking
Installed
new post and wire fencing
Completed the
new tarmac parking area
Installed
new block paving
Laid the
final slate dust top surface
Contractors
have also begun installing our new poly tunnel which includes a central paved area
and potting benches.
Today we received confirmation from contractors, Continental
Landscapes that any outstanding works, including the poly tunnel and potting
benches will be completed by the end of next week (Friday 20th July 2012). Suppliers of the timber building have also
confirmed that the building is in production and they are aiming towards delivering
the building to the site in approximately 4 weeks time.